Energy News South Africa

Load shedding necessary to avoid total system failure, says Eskom CEO

Eskom is obligated to implement load shedding in order to avoid a total system failure, said CEO Andre de Ruyter on Wednesday, 2 February, after the power utility announced that it would be implementing Stage 2 load shedding following breakdowns at its power stations.

“[We] would have the system equivalent of cardiac arrest. We have 50Hz going to zero and then to restart that system will take a period of between two to three weeks which clearly is a catastrophic event that we want to avoid at all costs. Therefore the implementation of load shedding is an effort to prevent this catastrophic blackout.

“So it is extremely unfortunate but it is the prudent step that our system operator takes and in this instance we have had to take this decision to implement Stage 2 load shedding,” De Ruyter said.

He said the current bout of load shedding had come after the grid came under severe pressure and emergency generating reserves ran too low.

“We have had some challenges on our generation systems…we have depleted our emergency reserves to the point where we risk not having adequate backup supply in the event of further failures in our generating system,” he said.

Multiple unexpected breakdowns

On Friday, during the state of the system media briefing, the utility said that the generating system was performing well.

Barely a week later, Eskom COO Jan Oberholzer explained that within hours of that briefing, multiple unexpected breakdowns over a period of 36 hours occurred which led to a point where the energy utility could not meet demand.

“We commenced [this] week with our diesel tank levels very low as well as the dam levels not full. We then continued to have some breakdowns, we had delays in returning some of the units and up until [Wednesday] we had even more breakdowns.

“[Some] of the units that were planned to return [to service] but didn’t have put us in this situation now that we do not have sufficient emergency resources. Our generating capacity is not where it’s supposed to be and so we cannot meet the demand of the country,” Oberholzer said.

“It may be that the system will improve and the breakdowns will not be where they are currently. There’s a possibility that we may lift it, however, it will depend on the successful return to service of the units as well as whatever breakdowns [may occur].

“The risk [of load shedding] remains. If we have a bad patch that we have had the last five or six days, we will definitely find ourselves wanting. But we will do whatever we can to make sure that we do not put the country through the strain of load shedding. We fully understand the mandate we have to the economy of the country,” he said.

Source: SAnews.gov.za

SAnews.gov.za is a South African government news service, published by the Government Communication and Information System (GCIS). SAnews.gov.za (formerly BuaNews) was established to provide quick and easy access to articles and feature stories aimed at keeping the public informed about the implementation of government mandates.

Go to: http://www.sanews.gov.za
Let's do Biz